by Toby Houldsworth | Jul 22, 2025 | News
Crushing Circuit ✅ Grinding Circuit ✅ Gravity Circuit ✅ Float circuit, under construction.
by Toby Houldsworth | Jun 13, 2025 | News
The New Underground Truck has arrived and now been commissioned underground, now hauling ore from our 1 Level North development to the Site ROM pad.
by Toby Houldsworth | Jan 13, 2025 | News
The first level brake through to historical workings has been completed, escape way established and first ore development completed.
by Toby Houldsworth | Aug 8, 2024 | News
Decline development has begun, full time handheld development commenced now at the Fiddlers creek mine. The Decline will be 2m wide by 2.5m high developed by Drill Blast Load Haul method. Current LOM 4.5 years.
by Toby Houldsworth | Aug 1, 2024 | News
Work has begun on the Hit and Miss to build the Wedderburn Milling Facility. The site is expecting to be operational in June 2025. The works will include the refurbishment of the primary crushing circuit, construction of the 5 T/H grinding circuit with Gravity and...